Nigeria Wins Key Legal Battle Over Mambilla Project Claims

On September 17, 2026, an International Chamber of Commerce arbitration tribunal in Paris ruled in favor of Nigeria in a long-standing dispute with Sunrise Power and Transmission Company Limited regarding the Mambilla Hydroelectric Power Project. The tribunal dismissed claims that could have exposed Nigeria to liabilities exceeding $3.38 billion.
This outcome is particularly significant as Nigeria faces challenges related to debt and infrastructure deficits. The Attorney General of the Federation and Minister of Justice, Prince Lateef Olasunkanmi Fagbemi (SAN), along with the Federal Ministry of Justice and Nigeria’s external defense team, which included Elizabeth Oger Gross and Tolu Obamuroh from Paul Hastings LLP, played crucial roles in this legal victory.
The dispute traces back to a 2003 agreement and escalated when Sunrise initiated arbitration in 2017. Although a settlement agreement in 2020 proposed a $200 million payment to Sunrise, the tribunal's recent ruling has raised questions about the conduct of public officials in such agreements.
Plus234Feed summary based on reporting from The Authority. Read the original report below.
Read full article
Continue on The Authority
Get the week in one email
Top stories, NPFL results, the naira — every Friday morning. Free, one email a week.
Related Stories

Nigeria Wins Arbitration Against Sunrise Power Over Corruption
Nigeria defeats Sunrise Power in $2.35bn arbitration case
Nigeria's Mambilla Hydropower Arbitration Concludes in Paris

Malami and Fagbemi Clash Over ICC Ruling on Mambilla Project

Sunrise Power's USD 2.35B Claim Dismissed in Paris

Sunrise Power's $2.35bn Claim Against Nigeria Dismissed
Get Plus234Feed on messaging apps
Same headlines, delivered where you already scroll.