TCN Restores Benin-Omotosho 330kV Line After Outage
The Transmission Company of Nigeria (TCN) successfully restored the Benin–Omotosho 330kV transmission line at 7:05 PM on Thursday, July 2, 2026, following a week-long outage that began on June 25, 2026. The outage was caused by a detached conductor that disrupted electricity transmission along the corridor.
TCN's engineering team immediately commenced repair work, which included restringing the detached conductor and conducting maintenance to ensure the safe restoration of the line. With the transmission line back in operation, three electricity distribution companies—Benin Electricity Distribution Company, Eko Electricity Distribution PLC, and Ikeja Electricity Distribution Company—will be able to receive an increased power supply for distribution to their customers.
TCN expressed regret for the inconvenience caused by the outage and thanked affected customers and stakeholders for their patience and cooperation during the repair period. TCN reaffirmed its commitment to maintaining a reliable and efficient national transmission network to support improved electricity supply across the country.
Plus234Feed summary based on reporting from The Authority. Read the original report below.
Read full article
Continue on The Authority
Get the week in one email
Top stories, NPFL results, the naira — every Friday morning. Free, one email a week.
Related Stories

TCN Restores Power on Benin/Omotosho 330kV Line

TCN Extends Jos-Gombe Line Maintenance Until June 2026

TCN Restores Power to Lagos After Grid Disturbance
TCN Completes Live-Line Maintenance on Zaria-Funtua Line

TCN Announces Daily Power Outages in Delta for Maintenance

TCN Schedules Planned Power Outage in Abuja for Maintenance