Joseph Tegbe Announces Major Power Projects for Abuja, Lagos

On October 29, Power Minister Joseph Tegbe announced that new electricity projects approved for Abuja and Lagos will necessitate months of transformer production before improvements can be delivered to consumers. The Federal Executive Council approved three projects during its meeting on October 28, which include works at Katampe in Abuja, the supply of three high-capacity transformers for the Lagos network, and a transmission line upgrade along the Lagos–Sagamu corridor.
Tegbe stated that the 300MVA transformers must be specially manufactured, a process expected to take between three and six months, which includes production, delivery, installation, and testing. The Katampe project will involve underground and overhead double-circuit lines connected to the transmission substation.
The Lagos–Sagamu corridor will see a 35.6-kilometre, 132kV line reconstructed from a single-circuit to a double-circuit configuration to meet additional electricity demand. The approval for the Lagos transformers includes design, manufacture, and supply, but the exact receiving substation remains to be confirmed.
Tegbe noted that Nigeria does not currently produce such large transformers domestically, necessitating overseas manufacturing.
Plus234Feed summary based on reporting from The Will. Read the original report below.
Read full article
Continue on The Will
Get the week in one email
Top stories, NPFL results, the naira, every Friday morning. Free, one email a week.
Related Stories

Federal Government Initiates 24-Hour Power Supply Plan

TCN Schedules 20-Minute Power Outage in Suleja

Federal Government Boosts Kano's Power Supply with New Substations

Nigeria's Power Minister Tegbe Unveils 300 Container Upgrade

Minister Joseph Tegbe Launches Power Projects in Kano, Katsina

Nigeria's Power Minister Unveils N1.2 Trillion Electricity Plan
Get Plus234Feed on messaging apps
Same headlines, delivered where you already scroll.