Minister Joseph Tegbe Launches Power Projects in Kano, Katsina

On October 26, 2026, Joseph Tegbe, the Minister of Power, inaugurated several transmission substation projects in Kano and Katsina States, adding 240MW at the 330kV level and 376MW at the 132kV level to Nigeria's transmission network. The projects are designed to strengthen bulk electricity supply, alleviate pressure on existing substations, and enhance power delivery to various consumers.
In Katsina, Tegbe commissioned two 60MVA power transformers at the Kankia Transmission Substation, increasing its capacity from 60MVA to 150MVA. He also initiated the construction of a new 120MVA transmission substation at Mashi and inspected ongoing work on a 200MVA gas-insulated substation at the 330kV Katsina Substation.
The new substation is expected to provide an additional 96MW upon completion. In Kano, Tegbe commissioned projects at Walalambe, Kumbotso, Dakata, and Dan Agundi substations, including multiple transformers.
Sule Abdulaziz, the Managing Director of TCN, stated that these projects would address transmission capacity constraints and improve electricity delivery.
Plus234Feed summary based on reporting from This Day. Read the original report below.
Read full article
Continue on This Day
Get the week in one email
Top stories, NPFL results, the naira, every Friday morning. Free, one email a week.
Related Stories

Federal Government Boosts National Grid with 640MW Capacity

TCN Boosts National Grid with 640MW from New Substations

Federal Government Boosts Kano's Power Supply with New Substations

Federal Government Launches 120MVA Power Substation in Katsina

Federal Government Boosts Kano Power Grid Capacity by 544MW

TCN Launches Kano-Katsina 330kV Power Project
Get Plus234Feed on messaging apps
Same headlines, delivered where you already scroll.