AEDC Restores Power Supply to Abuja After Technical Issues

The Abuja Electricity Distribution Company (AEDC) announced on August 27 that normal power supply has been restored to Abuja and other areas within its franchise following the resolution of technical issues on transmission lines from the Shiroro Transmission Station. This announcement comes amid a dispute between AEDC and the Transmission Company of Nigeria (TCN) regarding the cause of a recent drop in electricity supply to the Federal Capital Territory, where AEDC reported a decrease in power allocation from approximately 641 megawatts to 314 megawatts.
AEDC attributed this reduction to the tripping of 330kV transmission lines, a claim that TCN rejected as “inaccurate and misleading,” stating that the lines were operational and attributing the supply reduction to low power generation on the national grid. Despite the resolution, AEDC's statement did not directly address TCN's denial of the tripping claim, leaving both agencies with differing accounts of the situation.
Plus234Feed summary based on reporting from Daily Post. Read the original report below.
Read full article
Continue on Daily Post
Enjoy this article?
Get the weekly Nigerian roundup — top stories, NPFL, naira. One email, Sunday morning.
Related Stories

TCN Disputes AEDC's Claims on Abuja Power Supply Issues

Abuja Faces New Power Outage Due to Cable Fault

AEDC Starts Repairs at Maitama Substation After Crisis

Power Outages Expected in Abuja and Abia State on Sept 6

Power Outage in Abuja Due to TCN Maintenance Work

AEDC Announces Two-Week Power Interruptions in Abuja
Get Plus234Feed on messaging apps
Same headlines, delivered where you already scroll.