Abuja's Idu Zone to Get 24-Hour Power Supply by 2027

The Idu industrial area in Abuja is set to receive a 24-hour power supply through a 50-megawatt electrification project, following a ground-breaking ceremony. This initiative is a collaboration between Welbeck Electricity Distribution Limited, the Abuja Electricity Distribution Company (AEDC), and Shell Gas Limited.
The project will be executed in phases, with the first phase delivering 10MW by December 2026, and the remaining 40MW to be completed throughout 2027. Minister of Power, Joseph Tegbe, announced that the Federal Government is conducting technical audits across major industrial corridors, prioritizing the Lagos industrial axis, Abuja-Kaduna corridor, and Enugu-Onitsha axis.
Tegbe highlighted the importance of the Lagos corridor, which accounts for about 40% of national electricity demand, and aims to create approximately 180,000 jobs in six months. He also discussed the Electricity Act 2023's benefits and emphasized the need for community protection of power infrastructure to ensure sustainability.
Minister of State for Industry, John Owan Enoh, reiterated the government's strategy to promote local production and economic diversification.
Plus234Feed summary based on reporting from Blueprint. Read the original report below.
Read full article
Continue on Blueprint
Get the week in one email
Top stories, NPFL results, the naira — every Friday morning. Free, one email a week.
Related Stories

Nigeria's Government Launches 50MW Power Project in Abuja

Federal Government Initiates 24-Hour Power Supply Plan

TCN Schedules Six-Hour Power Outage for Maintenance in Abuja

AEDC Announces Two-Week Power Interruptions in Abuja
Power Supply Dispute Erupts Between AEDC and TCN

Power Outages Expected in Abuja and Abia State on Sept 6
Get Plus234Feed on messaging apps
Same headlines, delivered where you already scroll.